A new chapter the infinite tragicomedy
After the rejection of the original 2006 draft by the Supervisory Authority on procurement in violation of EU regulations and the subsequent referral to the Court of Auditors for loss of revenue, the
The initial estimates of expenditure amounting to € 2,550,000, however, remained unchanged. Work started in November 2008 and be completed by May 2010 have now started badly with constant delays of scheduled times, serious lack of organization and security standards, irregularities on the execution of concrete works such as to induce the supervisor to urge the City Council rescinded the contract for gross negligence of the company.
The town also agreed that the remains now visible are partially demolished and partially preserved, by accepting any possible risk to the future and used as a school building in the area recently classified as seismic.
in response to an tender issued last February and ended the 'April 8 while maintaining the same expenditure forecasts of 2006, the Board
The Mayor publicly praised the politicians promoting the benefits obtained in the recent election campaign, he has forgotten
assure the citizens of close monitoring of developments and the legitimacy of this unusual story
(Council information Boer appeared in the media in May)